§ 7.5-32. Permits.
(1)
Subdivisions: The department of planning and development issues the following permit for the construction of a subdivision:
A.
Land-disturbance permit. After the approval of the construction plans, this permit is issued for the implementation of erosion and sediment control measures as shown on the approved construction plans for all projects as required under article VII of this chapter.
B.
Reserved.
(2)
Commercial/industrial sites not involving the subdividing of land: The department of planning development issues the following two (2) permits for the construction of sites:
A.
Land-disturbance permit. After the approval of the construction plans, this permit is issued for the implementation of erosion and sediment control measures as shown on the approved construction plans for all projects as required under article VII of this chapter.
B.
Building permit. This permit is issued for the construction of proposed buildings. The building permit is issued after the site construction plans are approved, the building architectural plans are approved, and the land-disturbance permit is issued (if applicable). Appropriate permit fees shall apply.
(3)
Driveway permit. A review will be required of all new driveway cuts on a public right-of-way for the purpose of ensuring the requirements of these regulations are complied with and to determine if additional right-of-way improvements will need to be made by the property owner in order that the public right-of-way will accommodate the proposed vehicular use of said new driveway. When a building permit or land-disturbance permit is required, the driveway permit will be incorporated into said permits and no additional fees will be required. When no other permits are required, as stated herein, and a new driveway cut is made, a permit fee of fifty dollars ($50.00) will be required.
(4)
Pavement cut permit. A permit will be required prior to any work being done involving the cutting of any existing public right-of-way pavement. Said permit will be issued by the city public works department. (No permit fee is required.)
(5)
Displaying permits. Permits must be openly displayed on the site at all times.
(Ord. No. 32-98, § 1, 8-27-98; Ord. No. 59-00, 12-21-00; Ord. No. 60-00, 12-21-00; Ord. No. 68-04, § 5, 9-2-04; Ord. No. 51-08, § 1, 12-4-08)